Skip to content

Site Assessment Framework

Newfoundland & Labrador Ocean Cooling Site Selection

Document ID: CCNL-SAF-2024-01 | Version: 1.1 | Date: December 2025


1. Executive Summary

This document establishes the framework for evaluating potential sites for the Clean Compute NL ocean-cooled data center. The assessment considers oceanographic conditions, coastal infrastructure, grid connectivity, and environmental factors to identify optimal locations along the Newfoundland and Labrador coastline.

Priority Regions: 1. Avalon Peninsula (St. John's area) - Best grid/connectivity 2. Conception Bay - Sheltered, good access 3. Placentia Bay - Deep water access, industrial heritage 4. South Coast - Cold water proximity 5. Labrador Coast - Coldest water, remote


2. Oceanographic Assessment

2.1 Water Temperature Profiles

The Labrador Current brings Arctic water southward along the Newfoundland coast, maintaining cold temperatures year-round.

Temperature by Depth (Annual Average):

Depth Offshore NL Grand Banks Labrador Coast
Surface 5-12°C (seasonal) 3-15°C 0-8°C
50 m 2-6°C 2-8°C 0-4°C
100 m 2-4°C 2-5°C 1-3°C
200 m 3-4°C 3-4°C 2-3°C
400 m 3-4°C 3-4°C 3°C
Design Basis 3°C 3°C 2°C

Seasonal Variation at 200m Depth: - Maximum variation: ±0.5°C - This stability is critical for consistent cooling performance

2.2 Bathymetry Requirements

Parameter Minimum Optimal Notes
Pipe corridor depth 100 m 200-400 m Cold water access
Distance to 200m depth <10 km 3-5 km Pipe length economy
Seabed gradient <30° <15° Installation feasibility
Seabed type Consolidated Sand/gravel Pipe stability

2.3 Current and Wave Conditions

Labrador Current: - Speed: 0.1-0.5 m/s (10-50 cm/s) - Direction: Southward, parallel to coast - Depth: Extends to 500-600 m

Wave Climate (Offshore): - Significant wave height (annual avg): 2.5-3.5 m - Maximum recorded: 15+ m - Storm frequency: 20-30 days/year with Hs > 4 m

Ice Conditions: - Sea ice: December-May (variable) - Icebergs: March-July (200-800 per year in Iceberg Alley) - Design consideration: Pipes at >100 m depth avoid ice scour

2.4 Water Quality

Parameter Typical Value Impact on Design
Salinity 32-35 ppt Standard marine materials
Dissolved O2 6-8 mg/L Corrosion consideration
pH 7.8-8.2 Standard range
Turbidity Low Minimal fouling
Biofouling potential Moderate Closed loop eliminates

3. Coastal Infrastructure Requirements

3.1 Land Requirements

Component Area Required Notes
Data center building 50,000 m² 500,000 sq ft whitespace
Power infrastructure 10,000 m² Substations, switchgear
Cooling plant 5,000 m² HX, pumps, controls
Admin/support 3,000 m² Offices, security
Parking/roads 15,000 m² Access and staging
Buffer zone 20,000 m² Setbacks, expansion
Total Site ~100,000 m² ~25 acres

3.2 Shore Crossing Requirements

Factor Requirement
Beach type Sand/gravel preferred (for HDD)
Cliff height <20 m (manageable HDD)
Coastal erosion Stable or accreting
Shore protection Not in protected zone
Property access Industrial zoning or available

3.3 Construction Access

Requirement Specification
Road access Paved highway within 5 km
Heavy transport Capable of 50+ tonne loads
Marine access Harbor within 20 km for pipe delivery
Laydown area 20,000 m² for pipe storage

4. Grid Connectivity

4.1 Transmission Infrastructure

NL Hydro Transmission System:

Voltage Capacity Locations
230 kV 400+ MW Avalon, Central, Western
138 kV 100-200 MW Distributed
69 kV 50-100 MW Local distribution

Key Substations: 1. Holyrood (Avalon) - 230 kV, existing thermal plant site 2. Hardwoods (Avalon) - 230 kV, major node 3. Bay d'Espoir - 230 kV, hydro generation hub 4. Churchill Falls - 735 kV, major generation

4.2 Grid Connection Requirements

Parameter 100 MW Facility 200 MW Facility
Voltage 230 kV 230 kV
Dedicated line 5-20 km typical 5-20 km
Substation upgrade $15-30M $25-50M
Lead time 18-36 months 24-48 months

4.3 Power Quality

Parameter NL Grid Data Center Need Status
Voltage regulation ±5% ±3% May need conditioning
Frequency 60 Hz ±0.5% 60 Hz ±0.1% Acceptable
Outage rate 2-4 hrs/yr <1 hr/yr UPS/generator backup
Harmonic distortion <5% THD <5% THD Acceptable

5. Fiber Connectivity

5.1 Existing Infrastructure

Submarine Cables: - Hibernia Atlantic - Connects to Ireland/UK - ACORN - Atlantic Canada ring - Domestic backhaul - To Toronto/Montreal

Landing Points: - St. John's area - Limited alternative landing points

5.2 Connectivity Requirements

Parameter Minimum Optimal
Latency to Toronto <25 ms <20 ms
Latency to New York <30 ms <25 ms
Latency to London <50 ms <40 ms
Diverse routes 2 3+
Capacity 100 Gbps 1 Tbps

5.3 Connectivity Enhancement Options

  1. New submarine cable to US East Coast ($200-500M)
  2. Terrestrial backhaul upgrade through Quebec ($50-100M)
  3. Microwave backup for resilience ($10-20M)

6. Site Evaluation Criteria

6.1 Weighted Scoring Matrix

Category Weight Criteria
Ocean Conditions 30%
Water temperature 10% Colder is better
Distance to deep water 10% Shorter is better
Seabed conditions 5% Stable, gradual slope
Ice/storm exposure 5% Less is better
Infrastructure 35%
Grid proximity 15% Closer to 230 kV
Grid capacity 10% Available headroom
Fiber connectivity 10% Existing or planned
Land & Access 20%
Land availability 8% Industrial zoned
Road access 5% Highway proximity
Marine access 4% Harbor nearby
Workforce 3% Population center
Environment 15%
Protected areas 8% Avoid conflicts
Community support 5% Local acceptance
Visual impact 2% Manageable

6.2 Scoring Scale

Score Description
5 Excellent - Ideal conditions
4 Good - Minor limitations
3 Acceptable - Manageable issues
2 Marginal - Significant challenges
1 Poor - Major obstacles
0 Unacceptable - Fatal flaw

7. Candidate Site Analysis

7.1 Site A: Holyrood (Avalon Peninsula)

Location: Conception Bay South, former thermal plant site

Factor Score Notes
Water temperature 4 3-4°C at 200m
Distance to deep water 3 8-10 km to 200m depth
Seabed conditions 4 Gradual slope, known
Ice exposure 3 Moderate ice season
Grid proximity 5 Existing 230 kV substation
Grid capacity 5 400+ MW available
Fiber connectivity 4 15 km to St. John's
Land availability 5 Industrial site available
Road access 5 Trans-Canada Highway
Marine access 4 Conception Bay
Workforce 5 St. John's metro
Protected areas 4 No major conflicts
Community support 4 Positive (job creation)
Weighted Score 4.2 Top candidate

Advantages: - Existing industrial site with 230 kV power - Strong workforce availability - Good road and marine access - Established community relations

Challenges: - Moderate distance to cold deep water - May require pipe route optimization

7.2 Site B: Argentia (Placentia Bay)

Location: Former US Naval Base

Factor Score Notes
Water temperature 5 2-3°C, Grand Banks influence
Distance to deep water 4 5-6 km to 200m depth
Seabed conditions 4 Well-surveyed
Ice exposure 3 Moderate
Grid proximity 3 50 km to major substation
Grid capacity 4 Upgradable
Fiber connectivity 3 Requires extension
Land availability 5 Large industrial zone
Road access 4 Good highway
Marine access 5 Deep water port
Workforce 3 Smaller local population
Protected areas 4 Clear of protected areas
Community support 4 Economic development priority
Weighted Score 3.9 Strong candidate

Advantages: - Excellent ocean conditions - Large available land - Deep water port access - Government development support

Challenges: - Grid connection requires investment - Fiber extension needed - Smaller local workforce

7.3 Site C: Come By Chance

Location: Industrial area, existing refinery infrastructure

Factor Score Notes
Water temperature 4 3-4°C
Distance to deep water 3 10 km+
Seabed conditions 3 Variable
Ice exposure 3 Moderate
Grid proximity 4 138 kV available
Grid capacity 3 Upgrade needed
Fiber connectivity 3 Extension required
Land availability 4 Industrial zoning
Road access 5 Trans-Canada
Marine access 4 Existing terminal
Workforce 3 Local + commute
Protected areas 4 Industrial buffer
Community support 4 Diversification welcome
Weighted Score 3.5 Viable option

7.4 Site D: Bay Bulls (South Avalon)

Location: Fishing community, offshore supply base

Factor Score Notes
Water temperature 5 Cold current proximity
Distance to deep water 5 3-4 km to 200m
Seabed conditions 4 Well-surveyed (oil/gas)
Ice exposure 3 Moderate
Grid proximity 3 40 km to substation
Grid capacity 3 Requires upgrade
Fiber connectivity 4 Near St. John's
Land availability 2 Limited industrial land
Road access 4 Highway access
Marine access 4 Offshore supply base
Workforce 4 Commute from St. John's
Protected areas 3 Near Witless Bay reserve
Community support 3 Mixed (fishing interests)
Weighted Score 3.5 Good ocean, land limited

7.5 Site Ranking Summary

Rank Site Score Primary Advantage Key Challenge
1 Holyrood 4.2 Infrastructure ready Ocean distance
2 Argentia 3.9 Ocean conditions Grid extension
3 Bay Bulls 3.5 Cold water access Land availability
3 Come By Chance 3.5 Industrial base Grid capacity

8. Environmental Considerations

8.1 Protected Areas to Avoid

Area Type Location Buffer
Witless Bay Seabird Reserve South Avalon 5 km
Cape St. Mary's Seabird Sanctuary Placentia 5 km
Terra Nova National Park Bonavista 10 km
Eastport Marine Protected Bonavista 5 km
Gilbert Bay Marine Protected Labrador 10 km

8.2 Species Considerations

Species Concern Mitigation
Atlantic Cod Spawning areas Avoid known grounds
Capelin Beach spawning Time construction
Seabirds Nesting colonies Maintain distance
Whales Migration routes Slow vessel speeds
Seals Haul-out sites Avoid disturbance

8.3 Environmental Assessment Requirements

Assessment Trigger Timeline
Provincial EA >10 MW facility 6-12 months
Federal EA (IAAC) Marine component 12-24 months
DFO Authorization In-water work 6-12 months
Species at Risk If present Concurrent

9. Regulatory Framework

9.1 Jurisdictional Overview

Important: This project involves non-petroleum offshore infrastructure. The Canada-Newfoundland and Labrador Offshore Petroleum Board (C-NLOPB) does not have jurisdiction. Key regulators are:

Agency Jurisdiction Role
Impact Assessment Agency of Canada (IAAC) Federal EA Lead federal reviewer for major projects
Fisheries and Oceans Canada (DFO) Marine habitat Fisheries Act, Oceans Act, SARA
Transport Canada Navigation Navigation Protection Act
NL Dept. of Environment Provincial EA Environmental Protection Act
NL Dept. of Industry, Energy & Technology Energy projects Electricity generation/transmission
Crown Lands (NL) Seabed tenure Subsea lease/license

9.2 Key Permits Required

Permit Agency Purpose Timeline Complexity
Federal Impact Assessment IAAC Major project review 12-24 months High
Fisheries Act Authorization DFO Fish habitat alteration 6-12 months Medium
Navigation Protection Act Transport Canada Marine safety 6 months Low
Provincial EA Registration NL Environment Project screening 6-12 months Medium
Development Permit Municipal Land use approval 3-6 months Low
Crown Land Lease NL Lands Seabed access 6-12 months Medium
Electrical Permit NL IET Grid connection 3-6 months Low

9.3 Federal Impact Assessment Process

Under the Impact Assessment Act (2019), the project may trigger federal review based on: - Marine component (subsea pipeline >10 km) - Fish habitat interaction - Federal lands or funding involvement

IAAC Process (if designated):

PHASE 1: Planning (180 days)
├── Initial project description submitted
├── IAAC determines if assessment required
├── Indigenous engagement begins
├── Public comment period
└── Tailored guidelines issued

PHASE 2: Assessment (300 days, extendable)
├── Proponent prepares Impact Statement
├── Technical review by federal authorities
├── DFO, Transport Canada, Environment Canada input
├── Indigenous consultation
└── Public hearings (if required)

PHASE 3: Decision (30 days)
├── IAAC recommendation to Minister
├── Ministerial decision
└── Conditions of approval

TOTAL: 18-24 months typical

9.4 Provincial EA Process

NL Environmental Assessment Regulations require registration for: - Electrical generating facilities >10 MW - Industrial facilities with marine components

Provincial EA (concurrent with federal):

Registration → Public review (35 days) → Decision
            If concerns: Environmental Preview Report
            If significant: Full EIS

9.5 DFO Considerations

Fisheries Act (Section 35): Authorization required for work causing "death of fish" or "harmful alteration, disruption or destruction of fish habitat (HADD)."

Activity Potential Impact Mitigation
Pipe installation Temporary seabed disturbance Timing windows, silt curtains
Pipe burial Habitat alteration Restoration, offsetting
Heat discharge Localized warming Minimal (closed loop, diffuse)
Vessel traffic Marine mammal disturbance MMO, slow-down protocols

Species at Risk Act (SARA): Screening required for: - North Atlantic Right Whale (critical habitat nearby) - Atlantic Cod (COSEWIC assessed) - Leatherback Sea Turtle (seasonal)

9.6 Indigenous Consultation

Duty to Consult: Federal projects require meaningful consultation with Indigenous groups whose rights may be affected.

Group Territory Engagement Priority
Qalipu First Nation Island of Newfoundland High
Miawpukek First Nation South coast NL Medium
NunatuKavut Community Council Southern Labrador Site-dependent
Nunatsiavut Government Northern Labrador Site-dependent

Best practice: Engage early (pre-application), provide capacity funding, incorporate traditional knowledge.

9.7 Regulatory Timeline (Optimistic)

Month 0-3:     Pre-consultation meetings (IAAC, DFO, Province)
Month 3-6:     Initial project description filed
Month 6-9:     IAAC planning phase, guidelines issued
Month 9-15:    Impact statement preparation
Month 15-21:   Technical review period
Month 21-24:   Decision and conditions
Month 24-30:   Detailed permits (TC, Crown Lands, Municipal)
Month 30+:     Construction start

Total regulatory timeline: 24-30 months (can run concurrent with engineering)

9.8 Regulatory Risk Mitigation

Risk Mitigation Strategy
IAAC designation uncertainty Early engagement, request guidance
Indigenous opposition Early partnership approach, benefits agreements
Fishing industry concerns Stakeholder committee, compensation framework
SARA species presence Baseline surveys, seasonal restrictions
Timeline extensions Submit complete applications, dedicated regulatory lead
Cumulative effects Address in regional context

9.9 Regulatory Advantages

  1. Novel technology - No direct regulatory precedent, but closest analogues (submarine cables, SWAC systems) have been permitted
  2. Closed loop - No water intake/discharge = simplified DFO review
  3. Minimal thermal impact - Heat diffuses over 10 km, no plume
  4. Economic benefits - Government motivated to facilitate job creation
  5. Clean energy alignment - Supports federal/provincial climate goals

10. Site Development Sequence

Phase 1: Site Confirmation (6 months)

Activity Duration Deliverable
Geophysical survey 2 months Seabed mapping
Oceanographic study 3 months Temperature profiles
Geotechnical investigation 2 months Soil conditions
Environmental baseline 4 months Species survey
Grid study 3 months Connection plan
Decision gate Site selection

Phase 2: Permitting (18 months)

Activity Duration Deliverable
EA preparation 4 months Registration document
EA review 6 months Decision
Permit applications 6 months All permits submitted
Permit decisions 6 months Approvals received

Phase 3: Detailed Engineering (12 months)

Activity Duration Deliverable
FEED study 6 months Preliminary design
Detailed design 6 months Construction drawings
Procurement 6 months Major equipment orders
Contractor selection 3 months Construction contracts

11. Recommendations

Rationale: - Best overall infrastructure readiness - Existing 230 kV grid connection - Strong workforce availability - Industrial zoning in place - Community familiar with large industry - Manageable ocean access with engineering

Rationale: - Superior ocean conditions - Large land availability - Government development priority - Deep water port access - Grid and fiber can be extended

11.3 Next Steps

  1. Immediate: Commission oceanographic survey at Holyrood
  2. 30 days: Initiate pre-consultation with regulators
  3. 60 days: Engage NL Hydro on connection study
  4. 90 days: Complete site option report
  5. 120 days: Government briefing on site selection

12. Appendices

Appendix A: Bathymetric Data Sources

  • Canadian Hydrographic Service charts
  • Offshore petroleum survey data
  • Research vessel multibeam surveys

Appendix B: Climate Data

  • Environment Canada weather stations
  • Ocean Networks Canada buoys
  • Fisheries and Oceans temperature profiles

Appendix C: Grid Maps

  • NL Hydro transmission system map
  • Substation capacity data
  • Planned infrastructure upgrades

CCNL-SAF-2024-01 v1.1